Monday, November 23, 2009

Tech Meeting Canceled


The Technical Committee meeting scheduled for Tuesday 11/24 has been canceled. New meeting dates for the week of 12/07 have been posted on TimeBridge.

Saturday, November 21, 2009

Subscriber Programming

Below are the first set programming dates/times:

> Mon 11/30 0800 to 1600 @ Station 101: Worthington Fire

> Tues 12/01 0700 to 1500 @ Station 101: Worthington/Sharon/Perry PDs

> Wed 12/02 TBD @ Station 101: Remaining Worthington/Sharon/Perry Units

> Thur 12/03 0700 to 1500 @ WTFD Admin: Washington Fire

More dates/time to be announced

Wednesday, November 11, 2009

Connectivity Complete - STA Requests Submitted

All connectivity points are complete! The final connection to the prime site in Delaware was made late last night with the fiber runs and OARnet connection configurations are working as designed. The final bandwidth/latency testing is taking place and all sites will be actively passing data by Friday.

On the licensing front, the STA requests were filed today ask requested authorization to go on the air using the pre-rebanded frequencies. Approvals by the frequency advisor and the FCC are pending.

Tuesday, November 3, 2009

Connectivity Update

The fiber links between the Dublin Justice Center to Hard Road and to Worthington PD are up and running. Testing units are connected. Preliminary tests look good and will be left running for 24 hours to verify.

In addition, the T1 line between Worthington PD and Huntley Road, and the T1 lines between the Dublin Justice Center and Avery Road have completed testing and are ready to go.

The fiber connection to the master site in Delaware is all that remains. Completion is expected by the end of the week.